Skip to Content
Streetsblog California home
Streetsblog California home
Log In
LA Metro

Beverly Hills Approves Accelerating Subway Construction, Wilshire Boulevard to Close

LongBeachize_Ad_Concepts
This article supported by Los Angeles Bicycle Attorney as part of a general sponsorship package. All opinions in the article are that of the author, and do not necessarily reflect those of LABA. Click on the ad for more information.
false

Last night the Beverly Hills City Council approved expediting Metro Purple Line subway construction taking advantage of reduced traffic due to the COVID-19 crisis. Starting tomorrow, construction will fully close a three-block portion of Wilshire Boulevard immediately east of Beverly Drive. The closure is anticipated to save Metro up to six months in building its Westside Purple Line Extension Section Two - anticipated to be open in 2025.

Wilshire Boulevard closure details - via Metro presentation
Wilshire Boulevard closure details - via Metro presentation
false
Metro subway construction will close Wilshire Boulevard immediately east of Beverly Drive starting tomorrow. Detour map via BH staff report
Metro subway construction will close Wilshire Boulevard immediately east of Beverly Drive starting tomorrow. Detour map via BH City
false

In addition to the Wilshire full closure, Beverly Drive (at Wilshire) will be closed for up to ten days in the next couple months. Short portions of Reeves Drive and Cañon Drive (at Wilshire) will also be closed.

The construction acceleration item was approved about six hours into yesterday's city council meeting.

Several councilmembers expressed concerns, including about noise and Metro's ability to re-open the street promptly. Though the closure could last up to three months, the city can direct Metro to re-open the street at any time - giving five days notice. If Metro were to fail to re-open the street promptly, the agency would have to pay the city escalating penalities.

Councilmember Mirisch, who described the acceleration as "making lemonade out of lemons," pressed for Metro to apply money saved toward financing an additional "north portal" subway entrance. For the Wilshire/Rodeo Station, the current plans include only one entrance on the south side of Wilshire. Beverly Hills is pushing for a second station entrance on the north side. Metro staff responded that there was "not an immediate savings" but that the current acceleration could help the agency "avoid cost overruns in the future."

Metro spokesperson Dave Sotero adds that the council's approval will allow Metro "to complete decking for the Wilshire Beverly/Rodeo station sooner than expected and will help us minimize future construction impacts to local businesses as they struggle to overcome the impacts of the COVID-19 health crisis."

There are still a lot of unknowns. The six-month time savings is based on a full three-month closure, which would see Wilshire re-opening in early July. If the COVID-19 crisis recedes well before then, the Wilshire closure could be much shorter, resulting in less time savings. Right now, Metro construction has not been significantly impacted by COVID-19, but there is some potential that unforeseen events could constrain construction work. New York and Boston have halted much construction due to COVID-19; something similar could potentially take place here.

As of a community webinar at noon today, Metro staff stated that the full closure of Wilshire is planned for tomorrow, though, like everything these days, that timing is "subject to change." Metro also reported that, for the Purple Line Extension Section 3, Metro has already been working with the city of L.A. Transportation Department (LADOT) to take advantage of reduced traffic volumes in the Westwood area to accelerate some lane closures needed for early construction activities.

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Covina to Begin Construction on Recreation Village

The new facility will be next to the Metrolink station and include a variety of opportunities for fitness and amusement

July 26, 2024

Talking Headways Podcast: Have Cities Run Out of Land?

Chris Redfearn of USC and Anthony Orlando of Cal Poly Pomona on why "pro-business" Texas housing markets are catching up to "pro-regulation" California and what it might mean for future city growth.

July 26, 2024

Friday’s Headlines

Oakland identifies sites for speed camera pilot; E-bike tariffs conflict with US climate policy; Pollution spikes around warehouses, shipping hubs; More

July 26, 2024

What the Heck is Going on with the State E-bike Incentive Program?

The program's launch has been delayed for two years, and currently "there is no specific timeline" for it. Plus the administrator, Pedal Ahead, is getting dragged, but details are vague

July 26, 2024

The Paris Plan for Olympic Traffic? Build More Bike Lanes

A push to make Paris fully bikable for the Olympics is already paying dividends long before the opening ceremonies.

July 25, 2024
See all posts