Metro's new 8.5-mile Crenshaw/LAX light rail line really is approaching the finish line. According to testimony at yesterday's Metro board Executive Management Committee, staff reported that Crenshaw segments A and B (explained below) are substantially complete, essentially meaning that they have passed from the contractor's responsibility to Metro's responsibility. After substantial completion, Metro generally needs about six months to test the line, to train operators, and to work out any problems - prior to opening to the public.

Overall, Crenshaw/LAX construction is 99.6 percent complete, according to Metro's staff report.

If all goes well - which hasn't been the case for Crenshaw/LAX so far - the new rail line could open to the public as early as this December. Though early 2023 appears most likely.

Metro map showing Crenshaw/LAX line segments
Metro map showing Crenshaw/LAX line segments

The Crenshaw/LAX line extends through the cities of Los Angeles and Inglewood. Its northern terminus is at the Metro E (Expo) Line Crenshaw Station. Its southern terminus is at the Metro C (Green) Line Aviation Station. Initially, Crenshaw Line operations will be tied to the C Line and will not include the LAX station (though riders can utilize the Aviation Station shuttle). The LAX connection is a separate project - the Metro Airport Connector station, anticipated to open in 2024.

The completed segments A and B extend south from Leimert Park Station to the southern terminus.

The remaining segment C - the northern end of the line where it runs underground - is anticipated to be substantially complete by early June (as reported last month).

While a lot of focus has been on the Crenshaw/LAX line being late and over-budget (it had been anticipated to open in pre-pandemic Fall 2019), yesterday County Supervisor Sheila Kuehl expressed her excitement about the upcoming opening of the new line. "As I look at especially Crenshaw, the Airport Connector, the Regional Connector - thinking about the progress made through all these difficulties" Kuehl enthused, "I got really excited thinking about riding through my old neighborhood in Crenshaw, [and] the Regional Connector to go from one end [of the county] to the other on one train. It's exciting."

Kuehl thanked Metro CEO Stephanie Wiggins and all the Metro staff that "worked so hard to struggle through all of the setbacks," then gushed that "just listening to this made me feel like I want to hop on a train right now."

Map of Metro's nearly completed Crenshaw/LAX line
Map of Metro's nearly-completed Crenshaw/LAX line

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Friday’s Headlines

Caltrans, we need complete streets everywhere, including at freeway interchanges (or maybe especially there); Public agencies and academics join forces to develop AV standards; Republicans really want to suspend the gas tax; More

September 29, 2023

Transit Month Event: Disability Access is for Everyone

BART was the first accessible transit system in the country. Advocates want Bay Area transit agencies to do better at keeping buses and trains accessible for all

September 28, 2023

New Federal Committee Will Push for Transportation Equity By Helping DOT Reckon With Its Past

"Everybody who alive today and in a position of responsibility is accountable for what we do about transportation inequities. That's why we're here.”

September 28, 2023

Thursday’s Headlines

There's new transit funding available, CA needs to access it; Bus shelters are not some optional perk; Biking is up nationwide; More

September 28, 2023
See all posts