Metro Estimates West Santa Ana Branch Surface Heavy Rail Could Cost More Per Mile Than Purple Line Subway

For the West Santa Ana Branch, Metro staff is recommending three two-billion dollar tunnels, and ignoring a higher capacity surface heavy rail alternative. Map via Metro

Late last week, Metro released reports dismissing heavy rail as an option for its planned West Santa Ana Branch line. According to the Metro staff report, surface heavy rail on the WSAB would cost between $12.3 and $18.4 billion. The project is currently funded to the tune $4 billion, so, if Metro's cost estimates were grounded in reality, surface heavy rail would be prohibitively expensive.

For a full background, see Streetsblog's earlier editorial recommending Metro look at heavy rail.

Metro's WSAB heavy rail estimates show a cost of $0.67 billion to $1 billion per mile. That means, on a per-mile basis, Metro is estimating that WSAB surface heavy rail could cost Metro more than it currently costs to tunnel heavy rail subway below Wilshire Boulevard.

That's just not credible. Building a train on an existing ROW does not cost more than a whole new tunnel and tracks through downtown.

One problem appears to be that Metro's estimate is, according to the staff report, "based on recent Metro projects" which sounds like Metro is doing a surface rail estimate based on heavy-rail subway project costs, because Metro has not built surface heavy rail. Surface heavy rail - on an existing right-of-way - costs orders of magnitude less than Metro's upper project bound. Rail project costs vary around the U.S. and no two sites are exactly the same, which is why Metro should do some real math on this one, instead of blowing it off with bogus math. Metro's low-end estimate would mean that the WSAB would cost more than double per mile than any surface heavy rail project built in the U.S.

Meanwhile, Metro staff is recommending three light-rail subway alignments through downtown estimated to cost $5.4-$5.8 billion, with the caveat that "Cost estimates are expected to increase, resulting from further defining the project during the environmental review and public, stakeholder and partner engagement processes."

Each of Metro's three recommended routes include at least two miles of tunneling under downtown Los Angeles. The cost for the two-mile tunnel would likely be a bit more than the cost-overrun-plagued long Regional Connector subway, a 1.9-mile long LRT subway currently, halfway built, with a total project cost of $1.75 billion.

The reason Streetsblog suggested a heavy rail alternative on the line is it can use the existing subway tunnel from the southern part of the Arts District to get into downtown--so no new tunnels are required.

The WSAB item will be on this week's meetings of Metro's Planning and Programming Committee and Construction Committee.

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Tuesday’s Headlines

Maybe one day we'll take safety seriously.

December 16, 2025

State Grant Will Pay for Better Diesel Trains, Not Zero-Emission Trains, for Metrolink

I made a mistake covering the CTC grants last week that impacts a story Streetsblog has been covering. Let's set the record straight.

December 15, 2025

Monday’s Headlines

CA gets first win in fight over CAHSR funding. More wins needed.

December 15, 2025

Find Out Exactly How Much Downtown Highways Cost Your City

"How much does it actually cost to be car dependent?" This Dallas-based analyst set out to answer that question for cities across the U.S.

December 14, 2025

Eyes on the Street: Traffic Calming Rain Gardens Nearly Completed in Glendale

Sweet new sidewalk rain gardens are components of Glendale's 1.5-mile-long La Crescenta Avenue Rehabilitation Project. Also coming soon: bike lanes, decorative crosswalks, and more.

December 12, 2025

CalMatters Ponders State Inaction During Ongoing Traffic Safety Crisis

Yes, it's still a crisis even if the government doesn't do much about it.

December 12, 2025
See all posts