Memo Calls for Reconsideration of BART Extension Design

Note: GJEL Accident Attorneys regularly sponsors coverage on Streetsblog San Francisco and Streetsblog California. Unless noted in the story, GJEL Accident Attorneys is not consulted for the content or editorial direction of the sponsored content.

San Jose Mayor Sam Liccardo is concerned about a projected $3 billion cost overrun for the BART extension to downtown San Jose, attributed to designs that use a controversial single-bore, 85-foot-deep subway concept pushed by VTA.

Nevertheless, VTA is moving forward. From a San Jose Mercury News story about the VTA Board's decision Thursday to award contracts for the project. "VTA approves $235 million San Jose BART extension contract — so why is it also reviewing its controversial design?":

The unanimous vote from the board puts the VTA in the unusual position of awarding a $235 million contract that moves forward with the extension’s “single-bore” tunnel plan, while simultaneously launching a new analysis of the contentious design.

A map of the extension. Image: VTA
A map of the extension. Image: VTA
false

As reported previously, in an attempt to eliminate disruption to merchants, VTA had decided on a $9 billion deep, single-bore subway plan--which analysis shows could cost some $3 billion more than conventional tunneling--to construct the six-mile BART extension under downtown San Jose. VTA's preferred design would place the two tracks stacked one above the other inside a super-large, single tunnel (see comparative diagrams below). This single-bore construction technique can make sense in cities that need to avoid underground obstacles such as legacy subway tunnels (think London, Tokyo, etc). But, of course, there aren't any subways, crooked streets, or other such obstacles in San Jose.

VTA's design for a single, very deep bore through downtown San Jose. Image: BART
VTA's design for a single, very deep bore through downtown San Jose. This concept is supported by merchants because it minimizes temporary surface disruptions. Image: BART
false
The traditional, twin-bore configuration would have a max depth of 55 feet for riders, versus 85 feet for single-bore. Image: BART
The traditional, twin-bore configuration would have a max depth of 55 feet for riders, versus 85 feet for single-bore. Image: BART
false

But merchants always want transit in a subway, the deeper the better, with the belief that if it's deep underground construction will have no impact on their businesses. It also, however, means when the subway is finished riders will have longer trips to and from the platforms. It also complicates construction, fire safety, and operations, since trains can't switch from track to track without building complicated ramps between the two levels.

Nevertheless, it seemed San Jose politics have all but locked in the controversial, single-bore design, despite pushback from transit advocates. But at Thursday evening’s VTA board meeting, as reported in advocate Adina Levin's Green Caltrain blog, Mayor Liccardo submitted his memo calling for reviews of the project to explore:

  • Better connections at Diridon Station
  • Entrances at both sides of Santa Clara Street at the downtown station
  • Support for very high density transit oriented development

...and, most notably, an independent analysis comparing single-bore and dual-bore options, building on an earlier analysis done in 2017. Also from Green Caltrain:

"...the tradeoffs of the single and dual-bore options with regard to “passenger safety, rider access and experience, cost, and construction delay.” The previous analysis in 2017 had focused on constructability and operability, but did not compare the construction techniques for the ability to support better rider access and dense transit oriented development.

The memo from the Mayor is co-signed by San Jose Council Member and VTA board chair Chappie Jones, and Council Member Raul Peralez. Earlier this year, San Jose City Council had approved a resolution calling for improvements to the project relating to transit connections, multiple entrances, TOD, and alleviating construction impacts on businesses.

Since VTA originally made the decision in favor of the single bore option in 2018, concerns have grown regarding limitations in the project design and increasing cost estimates. SPUR and grassroots advocacy organizations such as the Transbay Coalition and Friends of Caltrain have called for passenger-focused improvements to the project, including adding entrances on both sides of the street, better passenger flow, better transit connections, and better support for transit-oriented development. A conventional subway design, with the train tunnels built side-by-side and far closer to the surface, makes it easier to accommodate such improvements.

Read more on the Green Caltrain blog and check out the coverage in the S.J. Merc News.

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Week Without Driving Day 4: Too Much Magic Bus

The Santa Rosa City Bus clearly prioritizes customer care, excellent service, and friendliness.

October 4, 2024

Friday’s Headlines

How Many Cars and People Use Great Highway Park?, SFMTA Looks at Expanding Definition of Recreational Vehicle, What's Behind Rage Against Scooters, Driverless Cars?, more...

October 4, 2024

Week Without Driving Day 3: The SMART Train

Our plan was to take the train to Larkspur and catch the ferry to San Francisco, where we would have lunch and shop at the Ferry Building.

October 3, 2024
See all posts