Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
false

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Skywalkermeme
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Op/Ed: The Cameras We Fear and the Speed We Ignore

We can hold two ideas at once. Surveillance systems that accumulate unchecked power deserve opposition. Tools that are narrow, transparent, and built with statutory guardrails deserve evaluation on their merits.

February 27, 2026

The Week in Short Video

Fresno ballot measures, wild armadillos, gas tax holidays, and four miles of mid-city Los Angeles subway opening in May

February 27, 2026

Friday’s Headlines

We wanted e-bike incentives. They offered EV rebates. But maybe we'll get nothing.

February 27, 2026

Americans Demand Congress Fund Active Transportation In Next Infrastructure Bill — And Not Just The Bike/Walk Advocates

A "back to basics" surface transportation bill — as Republicans are seeking — would be devastating for road safety and small businesses.

February 26, 2026

“Stop Super Speeders Act” Takes Aim at California’s Most Dangerous Drivers

Bill would stop super speeders after they're caught and hopefully before they kill.

February 26, 2026

SGV Bus Rapid Transit Gets Another $3.9M for Study and Design

Early improvements combine for about 14 miles of continuous bus lanes, expected to be installed in advance of the 2028 Olympic games.

February 26, 2026
See all posts