Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
false

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Skywalkermeme
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

The Week in Short Video

Rain gardens, bikes on trains, Uber on the ballot, Changes at CA High-Speed Rail, and reactions to ICE.

January 9, 2026

SGV Connect 145: Phoenix Tso of L.A. Public Press and the Altadena Fires

Struggles are plenty: insurance claims, fire remediation, lost income, lost neighbors and customers, and real estate development.

January 9, 2026

Friday’s Headlines

State of the state, ICE, and over a dozen headlines from up and down the state.

January 9, 2026

Confirmed: Non-Driving Infrastructure Creates ‘Induced Demand,’ Too

Widening a highway to cure congestion is like losing weight by buying bigger pants — but thanks to the same principle of "induced demand," adding bike paths and train lines to cure climate actually works.

January 8, 2026

Supervisor Wong Writes Legislation to Kill Sunset Dunes

District 4's new supervisor finally met with Sunset Dunes advocates the night before formally presenting legislation to put a new referendum on the ballot to destroy the park.

January 8, 2026
See all posts