Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
false

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Skywalkermeme
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

The Week in Short Videos

The videos are all upbeat! The Wonderful Protected Bike Lane Paving Machine, High-Speed Rail Progress, SB 79 Hearings, and Bakersfield is Pro-Bike.

August 29, 2025

Friday’s Headlines

Gav's CHP to Cities Order Draws a lot of attention, and the rest of the news from up and down the golden state.

August 29, 2025

Talking Headways Podcast: The Menace of Prosperity

Daniel Wortel-London on his new book, "The Menace of Prosperity: New York City and the Struggle for Economic Development, 1875–1981."

August 28, 2025

Thursday’s Headlines

Is the transit disaster in Philly a warning or a spoiler for the Bay?

August 28, 2025

L.A. Council Committee Approves Step toward Eliminating Parking Requirements

Off-street parking at new developments is not going away. If the city doesn't require parking, developers will still build parking.

August 27, 2025
See all posts