Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
false

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Skywalkermeme
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Monday’s Headlines

Local wins and federal challenges for transit; San Diego still looking for transit to airport; Too much solar power? More

November 25, 2024

Applications for Two Complete Streets Safety Assessment Programs Now Open

UC Berkeley's SafeTREC programs train groups to assess bicycle and pedestrian safety in their communities and identify safety improvements. Agencies and community groups are encouraged to apply.

November 25, 2024

Interview with Culver City Councilmember-Elect Bubba Fish

"I'm an advocate at heart who has been entrusted with the honor of a lifetime to represent my city on City Council."

November 25, 2024

Eyes on the Street: Horton Street Awesomeness

Emeryville's Horton Street sidewalk-level bike lane taking shape/almost completed. May we have some more please?

November 25, 2024

Should States Like Texas Be Allowed to Grade Their Own Highway Homework?

A carveout in federal law grants seven states authority to conduct their own environmental assessments on transportation projects. Texas abuses that power, advocates say.

November 25, 2024
See all posts