Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
false

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Skywalkermeme
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

The Week in Short Videos

Yes on Prop 50, No EV Rebates, Listen to StreetSmart!, and more money for states with a high percentage of married people.

September 26, 2025

Today’s Headlines

Too late, Tesla!

September 26, 2025

Advocates: Congress Must Stop Trump From Illegally Holding Back Sustainable Transportation Bucks

Congress has a chance to restore order, seize back their power of the purse, and stop Trump from "pocket-rescinding" hundreds of millions for good transportation projects.

September 26, 2025

Call to Action: Tell Mayor Lurie to Appoint an Interim District 4 Supervisor who Supports Car-Free Spaces

The Engardio recall doesn't directly endanger Sunset Dunes, but advocates want to get in front of the issue.

September 25, 2025

Newsom Names GM CEO Mary Barra as Villain in Fight with Feds over Air Quality

As the state battles the feds over EV funding, mandates, and rebates car company executives make good rhetorical foils. But they can't be held responsible for the state's shortcomings.

September 25, 2025

Thursday’s Headlines

Buses, and Bikes, and...Trump...oh, my!

September 25, 2025
See all posts