Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
false

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Skywalkermeme
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Thursday’s Headlines

For some reason people seem upset about gas prices. Oh well.

March 12, 2026

Talking Headways Podcast: Buildings are Here to Help People

Jeremy Wells on his book, Managing the Magic of Old Places: Crafting Public Policies for People-Centered Historic Preservation.

March 12, 2026

Bus Companies Say There’s a Better Way to Take a ‘Great American Road Trip’ This Summer

"Our eventual goal is to make inter-city bus travel every American's first consideration when they think about how to get from one city to the next."

March 11, 2026

Eyes on the Street: New Stations on Metro D Line Extension Section 2

After this May's D Line section 1 opening, there's more D to come! The D is growing longer! Check out photos of new station erection... er... construction today in Beverly Hills and Century City.

March 11, 2026

Op-Ed: Double Parking Likely Contributed to Inner Sunset Tragedy

This is yet another example of why protected bike lanes have to become the default in San Francisco.

March 11, 2026

Wednesday’s Headlines

Breaking: Building transit is good for transit ridership.

March 11, 2026
See all posts