Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

Construction started on SR-71 segment 1 less than two months ago and is already 3-6 months behind schedule. Segment 2, budgeted to cost $40 million now faces a $61M construction funding shortfall.
Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month’s Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already “three to six months behind schedule” due to “overhead power line conflict.”

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, “everything is going well” but “Caltrans has identified significant cost increases and potential schedule delays,” resulting in a “funding shortfall of up to $61M for the Construction Phase.” Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Streetsblog has migrated to a new comment system. New commenters can register directly in the comments section of any article. Returning commenters: your previous comments and display name have been preserved, but you'll need to reclaim your account by clicking "Forgot your password?" on the sign-in form, entering your email, and following the verification link to set a new password — this is required because passwords could not be carried over during the migration. For questions, contact tips@streetsblog.org.

More from Streetsblog California

Thursday’s Headlines

April 16, 2026

Pasadena Adopts Most of the 710 Stub Vision Plan

April 16, 2026

Talking Headways Podcast: Second-Hand E-Bikes Can Be The Way Forward

April 16, 2026

Commentary: Is a Transporter Bridge the 100-Year-Old Solution for the Estuary Crossing We’ve all been Looking for?

April 15, 2026

After Reelection Loss, Chair Fernando Dutra to Leave Metro Board

April 15, 2026
See all posts