Metro & Caltrans Under-Construction 71 Freeway Widening Project Hitting Cost/Schedule Overrun Snags

In July, Metro and Caltrans broke ground on their project to widen about 3.5 miles of the 71 Freeway through Pomona. The existing 4-lane State Route 71 will be widened to 8-lanes.

71 Freeway project description page - via Metro Highway Program presentation
71 Freeway project description page - via Metro Highway Program presentation
false

Construction is broken into two segments.

The first segment, under construction now, is from Rio Rancho Road to Mission Boulevard. Metro and Caltrans have already evicted about two dozen families from their homes in this area, and are currently pressing for a sole remaining household to relocate. This nearly two-mile segment is costing $174 million and is expected to be completed in 2024.

At this month's Measure M Independent Taxpayer Oversight Committee Meeting (presentation, listen to SR-71 item starting at minute 55:10), Metro staff reported that Segment 1 construction, which started July 17, is already "three to six months behind schedule" due to "overhead power line conflict."

Yes, you read that right: less than two months into construction, this segment is three to six months behind schedule.

The second segment runs from Mission Boulevard about 1.5-miles north to the 10 Freeway. This portion does not appear to involve the displacement of any additional homes, but is made somewhat difficult in that it involves replacing two historic railroad bridges.

Segment 2 was anticipated to cost $40 million and to start construction in Summer 2023. According to the Measure M presentation, "everything is going well" but "Caltrans has identified significant cost increases and potential schedule delays," resulting in a "funding shortfall of up to $61M for the Construction Phase." Metro, Caltrans, and The San Gabriel Valley Council of Governments are working to identify funding to complete the project.

Yes, you read that right: a $62 million shortfall on a $40 million project.

Skywalkermeme
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Quick-Build Legislation Makes It Through the Assembly

Following the success of Quick-Build projects in Santa Monica, their Assemblymember wants to allow them on state highways.

June 6, 2025

Friday’s Headlines

Tear your eyes away from the political drama and peep at these headlines

June 6, 2025

Glendora Celebrates New Metro A Line Station

As the rail line chugs toward its grand opening, officials are optimistic that there will be an extension into the Inland Empire.

June 6, 2025

Two Calls to Action: Petitions to Save Transit, Save Market Street

Advocates are making a full-court press to save Bay Area transit from suffering the same fate as Chicago and to stop Market Street from devolving into a car sewer.

June 5, 2025

Monrovia Breaks Ground on Park Honoring Japanese-American Poet Satoru Tsuneishi

Satoru Tsuneishi Park will be adorned with haikus written by the man who promoted the artform in America, before and after WWII.

June 5, 2025
See all posts