Skip to Content
Streetsblog California home
Streetsblog California home
Log In
LA Metro

Metro Expects to Finish Purple Line Extension Section One Tunneling This Week

Some new details emerged last week on Metro's herculean task of tunneling below Wilshire to extend the Purple Line subway.

Metro is extending its Purple Line (now renamed the D Line) subway westward in three sections. The $3 billion section one (WPLE1) will extend the line 3.9 miles under Wilshire Boulevard from Wilshire/Western Station to La Cienega Boulevard at the edge of Beverly Hills. WPLE1 construction began construction in 2014. The project is currently 68 percent complete and anticipated to open to the public in 2024.

In mid-2018, Metro’s two WPLE1 tunnel boring machines (TBMs) initially dug east from La Brea Avenue to Western. The TBMs were then transported back to La Brea and launched westward in October 2019. Tunneling under Wilshire west of La Brea - in the vicinity of the La Brea Tar Pits - has been slow. Metro had to temporarily pause tunneling many times due to obstacles including tar, methane gas, an abandoned oil well, and more. Those delays resulted in a $200 million (seven percent) WPLE1 budget increase, approved last October.

Last month, the first of WPLE1's two TBMs completed its work, breaking through at the site of the future La Cienega Station.

At last week's Metro board Construction Committee meeting [video - WPLE1 discussion starts at minute 9:37], Metro Executive Officer Project Management Sameh Ghaly noted that delays had further impacted the WPLE1 cost and schedule (that cost increase will return to the board after April). Ghaly reported that WPLE1 crews had successfully removed an "anomaly" - large pieces of steel. Ghaly announced that the second TBM was expected to complete its work Thursday or Friday - as soon as the day after tomorrow.

Responding to a question from Boardmember Fernando Dutra to explain what the anomaly was, Metro Chief Program Management Officer Richard Clarke described the challenges faced during WPLE1 tunneling:

As we were doing the tunneling, we encountered many unforeseen things... We decided that we should... probe ahead of the machine in case there was something unforeseen out there. We did that. And it picked up something... something in the ground that didn't seem to make sense. It wasn't congruent with the other ground conditions.

So we made the decision that we would stop the tunnel machines before it got there and figure out what this was and dig it out...

We got to the location. We had to grout from above to stiffen the earth, so as we dug ahead of the shield of the machine, so that the ground wouldn't settle or even worse.

That took a lot of time. We found, on one of the tunnels, a large H-beam that would have destroyed the shield. And just last week, or the week before, we found on the other tunnel... a large I-beam that would have done the same.

…if we had just not done that and had those pieces of steel destroyed the shield... (because once the machine would have been stopped there the only way we have seen to extract the damaged machine was from the surface - which would have meant shutting down the intersection of Wilshire and San Vicente...) it would have been a complete disaster, but we avoided the disaster but not without some cost to address it.

Metro was unable to determine what the "very heavy" metal beams were from.

Hopefully after this week, the unforeseen challenges will be in the past, and the focus can shift to completing the stations themselves.

Metro's Purple Line extension section 1 tunnel boring machines haven't had it easy. Photo by Joe Linton/Streetsblog L.A.
Metro's Purple Line extension section one tunnel boring machines haven't had it easy. Photo by Joe Linton/Streetsblog L.A.
false
Metro Westside Purple Line Extension Section 1 March 2021 status report - via Metro presentaton
Metro Westside Purple Line Extension Section 1 March 2021 status report - via Metro presentation
false

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Monday’s Headlines

Another study shows health benefits of biking far outweigh risks; Santa Rosa loses a freeway plan, gains a park; Take transit to the Rose Parade; More

December 23, 2024

New Metro Subway Railcars Started Service Today

Streetsblog got a special preview ride today. Have you ridden Metro's new "HR4000" heavy rail cars yet?

December 23, 2024

Letter to Readers: Happy Holidays and Thoughts on the Year’s Takeaways

2024 will be remembered as a seminal year for San Francisco streets

December 23, 2024

Streetsblog Year in Review: The Biggest Sustainable Transport News of 2024

It was a busy year in the movement to end car dependency — and there's a lot more to come.

December 23, 2024

Friday’s Headlines

New, wider sidewalks in SF's Tenderloin; Environmental groups sue CARB over biofuels; Biden sets national climate goals; More

December 20, 2024
See all posts