New Metro Sepulveda Transit Info: Draft Alignments, Estimated Costs and Ridership, Potential Freeway Stations

2:49 PM PDT on July 24, 2019

Metro is continuing to refine plans for its Sepulveda Transit Corridor Project, which will connect the Valley to the Westside. The plan is to create a transit corridor that roughly parallels the 405 Freeway. The Sepulveda line is anticipated to be heavy rail (HRT), though Metro is still studying the possibility of a monorail.

Four possible concept alignments for Sepulveda Transit
Metro's four possible concept alignments for Sepulveda Transit. HRT1-3 are heavy rail. MRT1 is monorail.

The Sepulveda project consists of two phases:

    • North: Extending from Westwood to Van Nuys. This ~12-15 mile section would connect to the existing Metro Expo Line, Orange Line, and Van Nuys Metrolink/Amtrak station - as well as to the future under-construction Westwood Purple Line station and planned Van Nuys light rail line - both of which would be completed before Sepulveda. Measure M schedules the north section to open 2033.
    • South: Extending from LAX to Westwood. This ~6 mile section would connect to the Expo Line and under-construction Crenshaw/LAX light rail. Measure M schedules the south section to break ground in 2048.

Starting tomorrow night, Metro will host a series of community input meetings on the Sepulveda project. For meeting details, see SBLA calendar or Metro project webpage. Streetsblog L.A. got a preview of some of the new project information to be presented and discussed at these meetings.

(Also this week, the Metro board will vote on initiating a Project Development Agreement (PDA) to lay the groundwork for a possible public-private partnership (P3) arrangement that could design, build, operate, and maintain the Sepulveda line. The PDA would not fully commit Metro to P3, but would make P3 project delivery easier.)

Costs

Measure M provides the lion's share of funding for the project. Based on the 2015 preliminary cost estimate, Measure M includes $5.7 billion for the initial North section. That 2015 allocation is adjusted upwards over time, so today it is about $6 billion. The project is the most expensive component of Metro's planned 28-by-2028 Olympics project acceleration. Now estimated at about $10 billion, Sepulveda accounts for roughly forty percent of the estimated $25 billion capital outlay needed for proposed acceleration.

That early estimate assumed less tunneling than is currently anticipated, especially at the north end of the line that preliminary plans had ending at the Metro Orange Line.

Metro's latest cost estimates for Sepulveda alternatives
Metro's latest cost estimates for Sepulveda alternatives

Earlier this year, Metro's preliminary cost estimate for the Sepulveda line was ~$8.6 billion. With further technical refinement, this amount has escalated to $10-$14 billion. Partially-elevated alignments - HRT3 and monorail - come in slightly cheaper than the other two, which are all tunnel.

Travel Time and Ridership

Metro has new estimates for travel times and ridership on the Sepulveda line.

Metro's estimates of Sepulveda line ridership and travel time
Metro's estimates of Sepulveda line ridership and travel time

Metro estimates that ridership would be slightly higher for HRT2 and HRT3 alignments, which include an addition Valley station at Sherman Way. Travel time is shortest for the more direct HRT1, which would take only sixteen minutes to get from Van Nuys Metrolink Station to the Expo Line. The monorail alignment would run slowest, as it takes a less direct aerial route over the Sepulveda Pass.

Metro estimates that the new UCLA Station would have 17,000-18,000 daily boardings - the highest of any non-transfer station in the Metro system.

Alignments

For the north section, Metro's alignments (at top of post) are nearly the same as what the agency announced in January. The only minor change is that Metro is studying a possible additional Santa Monica Boulevard station between Wilshire and Exposition.

There is plenty of new analysis on possible alignments for the southern section.

Metro Sepuveda line south alignments
Metro Sepuveda line south alignments
Additional Sepulveda transit south alignments
Additional Sepulveda transit south alignments

The southern section alignments for the Sepulveda line would run more or less beneath Bundy Drive/Centinela Avenue, the 405 Freeway, Sepulveda Boulevard, or Overland Avenue. Plans for this section are less fully developed than for the northern section.

Unfortunately several of the alignments under consideration include mid-freeway stations. Metro's existing freeway stations are hellish for riders. Pretty much all of them regularly violate Metro's standards for station noise. In addition, some existing Metro freeway rail has been plagued by vehicles crashing into rail infrastructure. These stations also subject riders to freeway pollution, and freeway-adjacent access that is nearly always uncomfortable and dangerous for walking. Improving freeway stations has been difficult due to working with Caltrans.

The northern section potentially includes freeway-adjacent stations along the 405 at Ventura Boulevard, Sepulveda Orange Line Station, and Sherman Way; at this stage all of these would be close by (just east of) the 405, but not in the center of it. Preliminary southern alignments show 405 Freeway-adjacent stations at Venice Boulevard and Sepulveda/Slauson/Jefferson.

Rendering of potential Metro station at Sepulveda and Ventura Boulevards
Rendering of potential Metro station at Sepulveda and Ventura Boulevards - including covering that could mitigate some noise issues from the adjacent 405 Freeway.

When questioned about issues with freeway stations, Metro staff shared the above Sepulveda/Ventura rendering suggesting that station design could help mitigate some of the negative aspects.

Ridership and travel time estimates for southern section of Metro Sepulveda line
Ridership and travel time estimates for southern section of Metro Sepulveda line

Travel time from the Van Nuys Metrolink Station to LAX is estimated to be 30-38 minutes.

Metro shared potential locations for a maintenance yard (MSF - Maintenance Service Facility.)

Potential Sepulveda line rail yard locations
Potential Sepulveda line rail yard locations

Learn more about Metro's Sepulveda Transit Corridor Project at this week's meetings.

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Op-Ed: Why Is Fare Evasion Punished More Severely than Speeding?

A.B. 819 offers California the opportunity to decriminalize fare evasion and replace punitive measures with more equitable approaches.

September 21, 2023

Eyes on the Street: Slow Streets in South Pasadena

The city has a sampler platter of quick-build temporary traffic calming installations to experience for the rest of the year

September 21, 2023

Thursday’s Headlines

The joys and risks of walking; Why is Fresno building so much parking? How much will breaking the law cost if you get caught by a speed camera? More

September 21, 2023

Metro Board Looks to Approve $65 Million for 91 Freeway Widening Projects

Metro staff are recommending the board approve funds to support two 91 Freeway expansion projects located in pollution-burdened communities in Southeast L.A. County - in the cities of Long Beach, Artesia, and Cerritos

September 20, 2023
See all posts