Skip to Content
Streetsblog California home
Streetsblog California home
Log In

It took eight years to build and cost $2.26 billion. It finally opened last month.

And now it's broken.

From an AC Transit release put out last night:

...a fissure has been discovered in a steel beam of the Salesforce Transit Center. The steel beam is located in the ceiling of the third level Bus Deck, on the eastern side, of the Transit Center near Fremont Street. Out of an abundance of caution, the TJPA has closed the Salesforce Transit Center until further notice.

Apparently the crack was discovered as workers were doing finishing work on the building. Streetsblog emailed a structural engineer who specializes in such failures. "It's rare for there to just be one crack," wrote the engineer, who commented on condition of anonymity. "They're going to find more. Steel doesn't crack for no reason."

[UPDATE 9/27 They found more.]

Should they close the terminal?

"Yes," replied the engineer, at least until they can figure out exactly what happened and how to fix it.

Police guarded Fremont Street under the Transit Center, now closed after a cracked beam was discovered
Police guarded Fremont Street under the Transit Center, now closed after a cracked beam was discovered in the Terminal, which passes overhead
false

The San Francisco Chronicle's John King interviewed Joe Maffei of Maffei Structural Engineering in San Francisco, who also made it clear that a structural beam simply should not crack. "Two possible culprits are a fabrication problem — something went wrong when the beam was manufactured — or the beam is supporting more weight than it’s designed to bear," he told the Chronicle.

AC Transit buses back at the familiar "Temporary" Transbay facility. And how temporary will it be now?
AC Transit buses back at the familiar "Temporary" Transbay facility. And how temporary will it be now?
false

Meanwhile, AC Transit buses, as seen above, have returned to the street-level Temporary Transit Center at Howard & Beale Streets, along with other agencies that use the center, including Muni and Golden Gate Transit.

Streetsblog took AC Transit in this morning and, certainly, the ride is longer without the dedicated ramp available into the Salesforce terminal and the slog through street-level traffic. However, the majority of the delay getting to downtown was still just getting across the bridge itself. Bus operators and passengers have had eight years to get used to the temporary center, and didn't seem to have any trouble returning to their old routine.

An aerial view of the rooftop park of Transbay. Pic: Transbay Joint Powers Authority
An aerial view of the rooftop park of Transbay. Pic: Transbay Joint Powers Authority
false

Do you take a Transbay bus as part of your commute? How much was it impacted by the closure? And what do you make of the unfortunate discovery. Post below.

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Monday’s Headlines

Everyone's talking about e-bike incentives...but there's more headlines from up and down the state.

April 28, 2025

Metro and Caltrans Break Ground on 105 Freeway Expansion

105 Freeway expansion is touted as "leaving a lasting legacy for Angelenos for decades to come" but it might not be the legacy that Metro and Caltrans think it is

April 25, 2025

USDOT Secretary Sean Duffy Is Dead Wrong About Bike Lanes

The Secretary of Transportation says he hasn't seen enough data to believe in the benefits of bike lanes. So we put together an explainer help him out — mostly using information from his own department.

April 25, 2025

Friday’s Headlines

Updates on Quick Build in Sacramento, Sunset Dunes in San Francisco, E-Bike vouchers everywhere and more...

April 25, 2025
See all posts