Skip to Content
Streetsblog California home
Log In
LA Metro

Metro Rail Shorts: Crenshaw and Connector Delays, Sepulveda Video, and More

11:31 AM PDT on May 12, 2021

Metro is busy building and planning for new rail lines, but it's not all going smoothly. Sure, mega-projects can have mega-hiccups, but Metro is continuing to make progress, and completion dates aren't all that far off. Below is a round-up of some recent Metro rail developments:

Report Forecasts Crenshaw Opening Forecast: November 2022

Metro's 8-mile $2 billion Crenshaw/LAX line has had more than its share of construction problems. When construction got underway in early 2014, the line was anticipated to open in fall 2019. It is getting difficult to keep track of the numerous times that Metro leaders have announced delays to that opening date, though it looks like the last projected opening date was late 2021.

In January, Metro announced that it had engaged a consultant to assess the project and come up with a more realistic schedule.

Twitter user Numble posted a March 2020 Crenshaw/LAX Montly Monitoring Report from the consultant, and the news is bad. The report forecasts that the line will open to the public (called revenue service) on November 1, 2022. The report contains a lot of near-impenetrable technical detail about various problems; for example, there were unacceptable gaps between the concrete bearing surface and the rail pads (this required a 50-person crew to grout.)

Construction is nearly complete, so much of the current work is testing everything, then troubleshooting and fixing systems that don't work. The report disparages an "abnormally low" rate of systems testing successfully, resulting in more time being spent to repair and re-test. "Failure rates are counterproductive. Assembly of key staff is difficult enough, and high failure rates are a set back to schedule and morale. [For systems testing] Team needs to prepare in advance and not waste time of approvers when obviously not ready."

DTLA Regional Connector Subway Opening Forecast: August 2022

Metro's 1.9-mile $1.8 billion downtown L.A. Regional Connector light rail subway broke ground in late 2014 and was expected to open in 2020. Tunneling through downtown was more difficult than anticipated, resulting in cost overruns and delays. In January, the board approved fiscal incentives expected to save time on the final stretch of construction (which has closed a portion of the L Line) and have the new line open to the public next Summer.

Twitter user Numble posted a March 2020 Regional Connector Monthly Monitoring Report that shows that the Regional Connector is still hitting some snags, though not quite as serious as those on Crenshaw. The report states that the connector opening has been pushed back about a month, now August 29 2022.

This appears to be the first time that the Regional Connector opening has moved ahead of Crenshaw/LAX opening. But they are still pretty much neck and neck. Fingers crossed for two big line opening celebrations next year.

New Sepulveda Explainer Video from Nick Andert

Those light rail projects are small potatoes compared to Metro's ~$10 billion Sepulveda Transit line. The always entertaining and informative Nick Andert has a new 27-minute long explainer video all about Sepulveda.

Spoiler: like Streetsblog, he doesn't have a high opinion of the monorail.

See also Andert's recent video updating overall Metro rail and BRT progress.

In Brief:

    • Cerritos and Artesia want West Santa Ana Branch rail to go underground at an intersection where Metro planned a cheaper aerial crossing (Numble)
    • In an email announcement, the Foothill Gold Line Construction Authority shared new plans for a rail bridge at the intersection of Bonita Avenue and Cataract Avenue in San Dimas. From the email: "The reconfigured intersection will converge at a more typical intersection angle, add new turn pockets, traffic signals, and reduce the total distance freight trains and pedestrians will need to travel to cross the diagonal crossing." Construction there is underway and expected to take about a year.
Rendering of xxx
Rendering of Bonita/Cataract bridge in San Dimas - via Gold Line Authority
Plans for
Plans for San Dimas Bonita/Cataract bridge and street realignment - via Gold Line Authority

Stay in touch

Sign up for our free newsletter

More from Streetsblog California

Eyes on the Station: Metro Fortified Turnstiles at MacArthur Park Station

Metro fortified turnstile entrances at MacArthur Park in order to curb fare-evading riders; sometimes this has adverse impacts on fare-paying riders

September 27, 2023

Streetfilms Tours Emeryville, the Little City that Can

Did somebody say "encore?" Safe streets rock star John Bauters, Mayor of Emeryville, population less-than 13,000, gave Streetfilms producer Clarence Eckerson a tour of his city

September 27, 2023

Guest Opinion: Metro Should Treat Walk and Bike Projects with the Respect They Deserve

Prioritizing true first mile/last mile infrastructure isn’t somehow optional; it’s how your customers get to and from the transit stations.

September 27, 2023

‘I’m Not Grieving Alone’: New Play Explores a Father’s Journey After Losing Two Children to Traffic Violence

Colin Campbell and his wife Gail Lerner lost both their children in a car crash with impaired driver. A new play explores how to talk about similar tragedies.

September 27, 2023
See all posts